    I was up against this last year, 130 Lenovo m75Q’s, how to fit 130 into a 42u rack including powerbricks. Solution was 3d printing.

  • linerror@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    you can replace the 17 power supplies with a server PSU… these should all be 12v DC input with a standard 2.1x5.5MM barrel connectors…

    flip them up onto their face, with the rear facing up. if you want to get fancy you could even make a base that integrates a little wedge and rod for the power button.

    get at least a 24 port switch and micro ethernet cables.

    this could be cleaned up to a single row on one shelf with no visible wires other than the ethernet and power lead running up and to the back. 1 switch under the machines… 1 PSU instead of 17… even one power cord…

    or a little cable management at the very least…

  • bryan_vaz@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    The setup is fine since you’re obviously trying to be budget conscience. I’d say cable management is really what you need more than anything else.

    However, if you’re handy with wood and a saw, or sheet metal and a brake (I assume you don’t have a 3d printer):

    • Stack them in sets of 4. The design of those NUCs allow them to be stacked without any thermal issues, as long as the ambient air is kept low enough.
    • Put the power supplies for each stack at the bottom of the stack in a 2x2 pattern (two side by side and stacked 2 high) - they should then match the footprint of each NUC
    • Set up a frame to hold each stack, I’d recommend 4 posts of 1/2"x2" flat stock wood (or 18GA steel strapping), 2 running along each side with 6"x6" platforms for each stack level to hold the frame together
    • For stack platforms at a minimum I recommend one at the bottom to hold your termination points (see below), one about 1" above the bottom one for the power supplies, one separating the power supplies and NUCs, and if you’re using sheet metal, one for each NUC. You can also add a cross bar at the top to use as a handle.
    • For power, those DC bricks use a standard C13 connector, so I would recommend a short length 4xC13-to-1xC14 splitter so that you only have one C13 input for the entire stack of 4 NUCs (if you’re in Asia, your local electronics shop should be able to make you a few splitters for pretty cheap if they don’t already have ones kicking around)
    • Both the NUCs and the DC bricks should be ziptied/string tied, or velco’ed to stack frame
    • Route the single C14 input to the bottom of the stack to the termination level (will probably be about 6"
    • Same for the network cables, run them down the side zip tied to frame and have them terminate at the bottom termination level. If you’re decent at terminating, or if you know someone who is fast at it, you can just crimp custom length cables for each of the 4 NUCs. Otherwise it should be 2x12" cables and 2x18" cables.
    • At the bottom I personally would recommend terminating with a CAT5e/CAT6 jack rather than a plug
    • Then orient your termination points so they point forward, that way all the cable hide at the back of the stack

    Once you have all your NUCs in modular stacks, you can just run network cables and C13 power cords neatly along the front of the shelf, and have them input at the bottom of each stack. Then just tie your runs to each stack in a neat bundle and mount your switches to the underside of those shelves.

    If you need to service a stack, you can just disconnect the stack in question at the termination points at the bottom of the stack and lift the whole assembly out, without having to play with wires. If you want to be extra fancy, you can even set up grooves or guides on the shelf to ensure the stacks are always placed in the correct position.

  • Professional-Fee2235@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    Personally I’d buy big power supply at the voltage it needs, get some board with fuses and connect all to that.

    But it seems you need few more shelves and pack of zip-ties first.

  • chandleya@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    This looks like a problem that would be solved cheaper with less mess by a used Lenovo Thinkstation P720, a pair of Xeon Gold 6140s, a dozen 32GB DIMMs, a 4TB NVMe, and a copy of VMware.

    Why on earth do you have so many minis?

    • NavySeal2k@alien.topB
      link
      fedilink
      English
      arrow-up
      1
      ·
      1 year ago

      To mitigate terminal server cost I guess. And no, virtualizing windows is no solution because to be legal you need expensive open license windows licenses and software assurance on that licenses …

  • theresmorethan42@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    Get a cheap UCS or super micro server on eBay. You can get a stupid number of cores and RAM for just about nothing, then you have one box, and altogether probably a LOT less power draw

  • gizzlyxbear@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    I only have a passing interest in homelab stuff, but I just wanted to say that I got really excited because I thought those were a bunch of PS2s. Thought this was gonna be some weird FFXI or Battlefront LAN system.

  • DonkeyOfWallStreet@alien.topB
    link
    fedilink
    English
    arrow-up
    1
    ·
    1 year ago

    10" racks

    Consolidate power might not be possible 12v? Even 20amps is 4-6 computers. Just get 10" pdu’s they have 3 plugs. I know there’s 17 computers and 3 switches that’s like 7 pdu’s…

    20 shelves

    2x 10u 10" racks…